In an MRP problem, A is an MPS item. Every A requires 3 B's and 2 C's. Every B requires 5 C's. All lead times are one period. Initial inventory values for all items are 0. Use lot-4-lot method for order quantities for all items. If gross requirement for A is 400 in period 10, what will be the planned-order release for C in period 8?
A) 800
B) 1,600
C) 6,800
D) 6,000
E) 1,200
Correct Answer:
Verified
Q81: If annual demand is 6,125 units, annual
Q82: In an MRP problem, A is an
Q83: Which of the following is not a
Q84: Which of the following is a dynamic
Q85: In an MRP problem, A is an
Q86: Which of the following is a dynamic
Q88: Under the lot-for-lot (L4L) lot-sizing technique as
Q89: If annual demand is 12,000 units, annual
Q90: Which of the following is a dynamic
Q91: In an MRP problem, A is an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents