A project team estimates that a work package is most likely to have a duration of 10 days. However, under the worst possible conditions pessimistic) it will take 40 days, and if conditions are ideal optimistic) , it will take only 4 days. Using the PERT three-point estimation method, what is the expected time for this work package?
A) 18 days
B) 14 days
C) 6 days
D) 26.67 days
E) 42 days
Correct Answer:
Verified
Q2: Which of the following types of precedence
Q3: Activity time estimates for the following project
Q4: Which of the following schedule display formats
Q5: The following network shows a portion of
Q6: The following network is the basis for
Q7: The following information is the basis
Q8: The following network is the basis for
Q9: Based on the table in the previous
Q10: The following software development plan is the
Q11: Which of the following is an example
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents