Hugh, SA, Recently Evaluated Its Manufacturing Process and Determined the Following

Question 1

Multiple Choice

Hugh, SA., recently evaluated its manufacturing process and determined the following about its main product:  Processing time 6 minutes  Move time 2 minutes  Inspection time 1 minute  Wait time 3 minutes \begin{array}{lc}\text { Processing time } & 6 \text { minutes } \\\text { Move time } & 2 \text { minutes } \\\text { Inspection time } & 1 \text { minute } \\\text { Wait time } & 3 \text { minutes }\end{array} The manufacturing cycle efficiency (MCE) for the product is


A) 1.00.
B) 0.75.
C) 0.67.
D) 0.50.