Let B = budgeted total cost for a work package T = estimated completion time for a work package
P = percent complete
A = actual expenses to date
M = time used to date
What is the definition of cost overrun, C?
A) C = A - PB
B) C = A - (1 - P) TB
C) C = A - PTB
D) C = A - MB/T
Correct Answer:
Verified
Q31: Ajax is about to embark on
Q32: A project contains activities D and K.Activity
Q33: Which of the following is not a
Q34: PERT/Cost is a cost-center based system, where
Q35: PERT/Cost:
A)allows for activity interruption.
B)assumes costs are evenly
Q37: Which of the following is false?
A)Crashing an
Q38: In using PERT/CPM, why does management need
Q39: Which statement does not represent a set
Q40: Which of the following is true?
A)Slack
Q41: Given the following data for work
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents