Which of the following is false?
A) Crashing an activity on the critical path can cause another path to become the critical path.
B) The maximum crash time reduction for each and every activity is limited.
C) CPM assumes that adding resources to crash an activity from its normal time to its crash time will reach a point of diminishing returns.
D) Crashing non-critical activities will not reduce the project time.
Correct Answer:
Verified
Q32: A project contains activities D and K.Activity
Q33: Which of the following is not a
Q34: PERT/Cost is a cost-center based system, where
Q35: PERT/Cost:
A)allows for activity interruption.
B)assumes costs are evenly
Q36: Let B = budgeted total cost for
Q38: In using PERT/CPM, why does management need
Q39: Which statement does not represent a set
Q40: Which of the following is true?
A)Slack
Q41: Given the following data for work
Q42: Explain the Excel functions
NORMINV(0.98,200,10)
NORMDIST(190,200,10,TRUE).
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents