A predecessor is a
A) resource that must be used before another resource.
B) view in MS Project.
C) task that must happen before another task.
D) task that must happen after another task.
E) task that must happen at the same time as another task.
Correct Answer:
Verified
Q7: The default view of MS Project is
Q8: MS Project stores information about
A)budgets
B)schedules
C)resources
D)tasks
E)all of the
Q9: MS Project is best described as a_product.
A)presentation
B)calendar
C)database
D)scheduling
E)spreadsheet
Q10: When you create subtasks the tasks associated
Q11: Subtasks are created and undone using the_
Q13: The _is located on the far left
Q16: Dependencies are reflected in the _screen.
Q17: In the resource view you see_available to
Q25: Task duration times are based on the
Q36: It is _ to show all the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents