The default view of MS Project is the
A) resource sheet.
B) Gantt chart view.
C) resource usage view.
D) budgets view.
E) tasks view.
Correct Answer:
Verified
Q2: The resource usage view allows the project
Q3: MS Project is a full -service project
Q4: In the Gantt chart the arrows that
Q5: All project management begins with
A)a project.
B)an understanding
Q6: MS Project allows a(n)_to create tasks.
Q8: MS Project stores information about
A)budgets
B)schedules
C)resources
D)tasks
E)all of the
Q9: MS Project is best described as a_product.
A)presentation
B)calendar
C)database
D)scheduling
E)spreadsheet
Q10: When you create subtasks the tasks associated
Q11: Subtasks are created and undone using the_
Q12: A predecessor is a
A)resource that must be
Unlock this Answer For Free Now!