When Determining the Sequence of Activities, the Project Manager Should

Question 23

Multiple Choice

When determining the sequence of activities, the project manager should take some constraints into account. These can fall into the following category/categories:


A) external dependencies.
B) schedule dependencies.
C) technical requirements and specifications.
D) none of the above.

Correct Answer: