An activity of zero duration that is used to show a logical relationship or dependency in a network diagram is called:
A) dummy activity.
B) activity node.
C) empty node.
D) dumb node.
Correct Answer:
Verified
Q21: Another term for a product breakdown structure
Q22: All of the following are estimation phases
Q23: When determining the sequence of activities, the
Q24: The scope baseline includes:
A)the project workbook and
Q25: The output that results from the process
Q27: The approach to creating a WBS where
Q28: A finish- to- finish dependency indicates that:
A)the
Q29: The need to start marketing efforts long
Q30: Schedules are:
A)often updated t incorporate project changes.
B)important
Q31: Work packages should be all EXCEPT:
A)completed by