A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project?
A) 8.00
B) 4.24
C) 2.82
D) 5.56
Correct Answer:
Verified
Q24: Keith welds a one-fourth-inch diameter ball bearing
Q27: The one element that Agile shares with
Q34: Wayne and Garth are engaged in XP
Q35: Extreme programming advocates a large development staff,several
Q36: A project consists of four activities with
Q46: Alexander Demetrius Dickson,ADD to his friends,has three
Q46: A project consists of four activities with
Q49: An important departure from traditional project management
Q51: Successful implementation of CCPM depends on first:
A)Identifying
Q55: Which statement about critical chain methodology is