Question 48

Multiple Choice

The expected return of Project Y is at least equal to the expected return of Project X, and the variance of Y is less than that of X. Using the mean variance rule, what would you do?


A) Reject both projects
B) Accept both projects
C) Prefer Project X
D) Prefer Project Y

Correct Answer: