An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is
A) 2.00.
B) 2.33.
C) 2.67.
D) 8.00.
E) 23.3.
Correct Answer:
Verified