Use the earned value table to determine the estimated time to completion given the indicated state of the project.
A) 52 days
B) 49 days
C) 58 days
D) 43 days
Correct Answer:
Verified
Q67: At the end of week 20,this project
Q68: The first step in earned value management
Q69: Use the earned value table for Project
Q70: Use the data to calculate the earned
Q71: In earned value management analysis,the cumulative amount
Q73: Use the data to calculate the schedule
Q74: The project baseline is established by combining
Q75: Use the earned value table to determine
Q76: The budget variance is calculated as:
A)earned value
Q77: Use the earned value table (all amounts
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents