The budget variance is calculated as:
A) earned value minus planned value.
B) planned value minus actual cost.
C) earned value minus actual cost.
D) cost minus planned value.
Correct Answer:
Verified
Q71: In earned value management analysis,the cumulative amount
Q72: Use the earned value table to determine
Q73: Use the data to calculate the schedule
Q74: The project baseline is established by combining
Q75: Use the earned value table to determine
Q77: Use the earned value table (all amounts
Q78: In earned value management,schedule variance is defined
Q79: Project Terrace has an actual cost of
Q80: Use the earned value table to determine
Q81: The Project Implementation Profile does NOT contain