Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Business
Study Set
Project Management Achieving Competitive Advantage Study Set 2
Quiz 9: Project Scheduling: Networks, duration Estimation, and Critical Path
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Question 1
True/False
Preceding activities are those that must occur before others can be done.
Question 2
True/False
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
Question 3
Essay
The late finish times are determined by taking a(n)________ through the network.
Question 4
Essay
A(n)________ is a point when an activity is either started or completed.
Question 5
True/False
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
Question 6
Essay
The amount of time that an activity may be delayed from its early start without delaying the entire project is ________.
Question 7
True/False
Burst activities are those with two or more successor activities.
Question 8
Essay
A(n)________ is a project schedule whose start and finish dates reflect expected resource availability.
Question 9
True/False
Float is always measured in exactly the same way as slack.
Question 10
Essay
________ is the identification of the project objectives and the ordered activity necessary to complete the project.
Question 11
True/False
At a burst point in a backward pass,the largest succeeding late start becomes the late finish for that node.
Question 12
True/False
In assigning a value for the most pessimistic (b)duration,the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.