Which estimating technique uses the cost from a previous project along with measures of scale to estimate the cost for a similar,future project?
A) analogous estimating
B) parametric estimating
C) bottom-up estimating
D) Monte Carlo estimating
Correct Answer:
Verified
Q6: Special cause variation arises when something out
Q10: Typically,expedited costs are preferred over regular costs.
Q13: Analogous estimating is the most detailed,time consuming
Q17: Project managers are encouraged to avoid overly
Q23: In addition to optimizing project costs,value engineering
Q25: Complex projects such as research and development
Q26: The documentation of a project cost estimate
Q27: There are many causes of variation in
Q34: Costs that repeat as project work continues
Q38: Which estimating technique decomposes the work into
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents