Complex Projects Such as Research and Development Projects Often Employ

Question 25

Multiple Choice

Complex projects such as research and development projects often employ rolling wave planning to estimate project costs. Which of the following best describes "rolling wave" planning?


A) Project managers render a definitive estimate for the next stage and an order of magnitude estimate for the remainder of the project.
B) Project managers render an order of magnitude estimate for the next stage and a definitive estimate for the remainder of the project.
C) Project managers render a definitive estimate for all stages of the project during the initiation stage.
D) Project managers render an order of magnitude estimate for all stages of the project

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents