For Each Component in the Work Breakdown Structure (WBS),the WBS

Question 29

Multiple Choice
For each component in the Work Breakdown Structure (WBS),the WBS dictionary includes:

For each component in the Work Breakdown Structure (WBS) ,the WBS dictionary includes:


A) the name of the originator
B) a list of concurrent activities from related work packages
C) the physical location where the work will be performed
D) none of these

Correct Answer: