For Each Component in the Work Breakdown Structure (WBS),the WBS

Question 34

Multiple Choice
For each component in the Work Breakdown Structure (WBS),the WBS dictionary includes all the following fields that will be progressively elaborated EXCEPT:

For each component in the Work Breakdown Structure (WBS) ,the WBS dictionary includes all the following fields that will be progressively elaborated EXCEPT:


A) a brief scope description
B) name of team member(s) that will be responsible for creating the deliverables
C) a list of associated activities
D) defined deliverables