A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity. What are the duration and the early start time associated with this hammock activity?
A) 13, 36
B) 7, 0
C) 13, 7
D) 7, 14
Correct Answer:
Verified
Q60: What is the slack time for Activity
Q62: Use the network diagram and activity lengths
Q63: Use the network diagram and activity lengths
Q66: Use the network diagram and activity lengths
Q67: Activities C, D, and E in the
Q68: A project has the precedence requirements and
Q69: Use the network diagram and activity lengths
Q70: Activities C, D, and E in the
Q78: There's an old saying,"The job is not
Q100: The overall effect of laddering activities is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents