Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.
A) 12
B) 13
C) 14
D) 15
Correct Answer:
Verified
Q48: An activity has an optimistic time estimate
Q57: What is the float start time for
Q58: What is the early start time for
Q60: What is the slack time for Activity
Q63: Use the network diagram and activity lengths
Q65: A project has the precedence requirements and
Q66: Use the network diagram and activity lengths
Q67: Activities C, D, and E in the
Q78: There's an old saying,"The job is not
Q100: The overall effect of laddering activities is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents