A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the feeder buffer for path NQT if this project is managed using critical chain methodology?
A) 9.0
B) 2.25
C) 4.5
D) 6.75
Correct Answer:
Verified
Q41: Your next project consists of 5 consecutive
Q42: If a project activity experiences positive variation:
A)the
Q57: Your next project consists of 8 consecutive
Q58: If a project activity experiences positive variation:
A)the
Q59: A project consists of three activities with
Q64: A project is represented by the activity
Q65: A project is represented by the activity
Q66: A system-wide constraint is called a(n):
A) rope.
B)
Q72: An important departure from traditional project management
Q85: In order to resolve a resource conflict,it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents