A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the feeder buffer if this project is managed using critical chain methodology?
A) 9.0
B) 7.5
C) 4.5
D) 6.0
Correct Answer:
Verified
Q41: Your next project consists of 5 consecutive
Q59: A project consists of three activities with
Q61: A project is represented by the activity
Q65: A project is represented by the activity
Q66: A system-wide constraint is called a(n):
A) rope.
B)
Q67: Use the project information in the table
Q72: An important departure from traditional project management
Q77: Subcontractor deliveries are difficult to schedule with
Q84: Which of the following statement is best?
A)The
Q85: In order to resolve a resource conflict,it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents