A project is resource leveled without resource-limited constraints and the project did not extend beyond its required completion after leveling.Which of the following must have been false?
A) The critical path of the project had negative slack.
B) Tasks using the same resources that were leveled were not on the critical path.
C) At least one of the activities using the resources that were leveled had positive slack.
D) The project had adequate positive slack in all the paths to accommodate the leveling.
Correct Answer:
Verified
Q35: Resource constraints are represented in the network
Q36: Resource requirements graphs based on an as-soon-as-possible
Q37: Technical constraints for a project are represented
Q38: Resource utilization charts based on each activity's
Q39: Activities in a network diagram are drawn
Q40: Which of the following is likely not
Q41: If three activities are using the same
Q42: When performing resource-limited scheduling, those activities with
Q43: If three workers are assigned to a
Q44: If not enough resources are available for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents