In PERT analysis, the probability of the optimistic time occurring should be on the order of
A) 1/3.
B) 1/6.
C) 1/10.
D) 1/100.
Correct Answer:
Verified
Q72: Table 11-4
The following represents a project with
Q73: In PERT, we assume that
A)the times to
Q74: Given an activity's optimistic, most likely, and
Q75: The project described by: Q76: Table 11-4 Q78: Given an activity's optimistic, most likely, and Q79: Given an activity's optimistic, most likely, and Q80: Table 11-4 Q81: Which of the following is not a Q82: An alternative approach to project crashing is
The following represents a project with
The following represents a project with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents