In PERT, we assume that
A) the times to complete individual activities are known with certainty.
B) all activities are carried out by staff from our own organization.
C) the total cost of a project is independent of the time to complete the project.
D) the total time to complete all activities on the critical path is described by a normal distribution.
Correct Answer:
Verified
Q68: Table 11-4
The following represents a project with
Q69: Your company is considering submitting a bid
Q70: Consider a project that has an expected
Q71: PERT stands for
A)probabilistic evaluation and review technique.
B)program
Q72: Table 11-4
The following represents a project with
Q74: Given an activity's optimistic, most likely, and