Five jobs are waiting for processing through two work centers.Their processing time (in minutes) at each work center is contained in the table below.Each job requires work center Sigma before work center Delta.According to Johnson's rule,what sequence of jobs will minimize the completion time for all jobs?
A) R-S-T-U-V
B) S-V-T-R-U
C) S-U-T-V-R
D) V-R-U-S-T
E) R-V-T-S-U
Correct Answer:
Verified
Q64: Average completion time for a schedule sequence
Q65: Eight jobs have been sequenced at a
Q66: What does the use of the shortest
Q67: Sequencing (or dispatching):
A) assigns dates to specific
Q69: Which of the following dispatching rules tends
Q74: What is the priority rule that sequences
Q79: Five welding jobs are waiting to be
Q87: _ determines the order in which jobs
Q88: _ determine the sequence of jobs in
Q100: A practitioner of family medicine begins her
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents