The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6. a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q61: Explain why the critical path is the
Q73: Define slack time.
Q76: The network below represents a project being
Q78: Draw the AOA and AON networks for
Q89: The _ distribution is used by PERT
Q89: A PERT project has 45 activities,19 of
Q92: A project being analyzed by PERT has
Q100: Which of the following statements regarding PERT
Q101: A project whose critical path has an
Q114: Describe in words how to calculate a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents