A PERT project has 45 activities,19 of which are on the critical path.The estimated time for the critical path is 120 days.The sum of all activity variances is 64,while the sum of variances along the critical path is 36.What is the probability that the project can be completed between days 108 and 120?
A) -2.00
B) 0.0227
C) 0.1058
D) 0.4773
E) 0.9773
Correct Answer:
Verified
Q84: The beta distribution is used in project
Q85: An activity on a PERT network has
Q87: Analysis of a PERT problem shows the
Q88: Which of the following statements regarding PERT
Q91: An activity on a PERT network has
Q92: A project being analyzed by PERT has
Q93: A project being analyzed by PERT has
Q98: An activity on a PERT network has
Q100: Which of the following statements regarding PERT
Q110: PERT calculations typically include the duration variance
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents