For which of the following would a p-chart be used?
A) Monitor the process means for samples.
B) Monitor dispersion in sample data.
C) Monitor the proportion of defectives in a sample.
D) Monitor the number of defects per unit.
E) Monitor the range of values in samples.
Correct Answer:
Verified
Q73: Which of the following is not needed
Q74: The term "2 sigma limits" in the
Q75: When using control charts sample size is
Q76: The DMAIC methodology involves all EXCEPT which
Q77: The probability of concluding that an assignable
Q79: When a process is judged out of
Q80: A shift in the process mean for
Q81: A Quality Analyst wants to construct a
Q82: For a process to be capable,it must
Q83: What should managers have in place if