Ignoring the Possibility of Safety Stock Requirements,which One of the Following

Question 51

Multiple Choice

Ignoring the possibility of safety stock requirements,which one of the following most closely describes the calculation of net requirements for an item in MRP?


A) Gross requirements - projected on-hand - scheduled receipts
B) Gross requirements - scheduled receipts
C) Gross requirements - order releases + amount on-hand
D) Gross requirements - planned order releases