Sequencing is concerned with the order in which jobs are processed,while loading is concerned with assigning jobs to work centres or workstations.
Correct Answer:
Verified
Q6: In job scheduling,most loading of work centres
Q7: A Gantt chart is a visual aid
Q8: Priority rules generally assume that a job's
Q9: The term loading,as used in scheduling,refers to
Q10: A load Gantt chart only designates the
Q12: In the production planning hierarchy,scheduling is the
Q13: First come,first served (FCFS)is an example of
Q14: Scheduling work centre loading must be completed
Q16: Loading refers to the assignment of jobs
Q39: Makespan is the total time needed to