Nodes not on the critical path contain ________ time and allow the project manager some flexibility in scheduling.
A) Shortest
B) Critical
C) Slack
D) Report
Correct Answer:
Verified
Q86: The acronym PERT stands for Program Evaluation
Q87: To construct the Gantt chart,a _ is
Q88: What is the critical path? Why is
Q89: Define and describe the PERT technique.
Q90: Which of the following is NOT a
Q92: What are some of the activities one
Q93: Which of the following is NOT a
Q94: _ is a critical path scheduling technique
Q95: The critical path represents the _ time
Q96: Microsoft Excel is an example of project