Which of the following is NOT a feature of a network diagram?
A) It represents how completion times vary for activities.
B) It is more often used than Gantt charts to manage projects such as information systems development.
C) Connecting arrows are not used.
D) Variability in the duration of activities is the norm.
Correct Answer:
Verified
Q85: A critical path refers to a sequence