Question 26

Multiple Choice

Mahie's team had to choose between two products to develop. The team made their decision and completed the production process. After a short while it became clear that the team made the wrong decision. Even so, the team continued to allocate resources to the product despite a substantial amount of feedback indicating that their choice had been wrong. This is an example of


A) risk propensity.
B) problem framing.
C) scapegoating.
D) escalating commitment.

Correct Answer: