A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day.The tasks necessary to produce this product are detailed in the table below.
a.Draw the network described in the table.
b.Without regard to a production schedule,what is the minimum possible cycle time (in seconds)for this situation;what is the maximum?
c.What is the required cycle time (in seconds)in order to meet the schedule?
d.What is the theoretical minimum number of workstations needed to meet the schedule?
e.Balance this line using longest processing time.
f.What is the efficiency of the balance obtained in part e?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q135: What is cross-docking?
Why is it appropriate
Q136: An assembly line has been designed to
Q138: "Having a focused work centre is like
Q143: An electronics manufacturer makes remote control devices
Q145: An airport is trying to balance where
Q146: Brandon's computer shop has hired a consultant
Q146: A firm is planning to set up
Q151: A work cell is required to make
Q213: What design guidelines help retail layouts to
Q254: Explain how a load-distance model helps solve
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents