A production line is to be designed for a job with four tasks. The task times are 2.4 minutes, 1.4 minutes, 0.9 minutes, and 1.7 minutes. After line balancing, the longest possible assigned task time is ________ and the shortest possible assigned task time is ________ minutes.
A) 1.8; 1.4
B) 1.6; 0.9
C) 6.4; 2.4
D) 2.4; 0.9
E) none of these
Correct Answer:
Verified
Q90: Daily capacity of a product layout is
Q93: In a product-oriented layout, the process of
Q94: Which of the following is true regarding
Q98: The assumptions necessary for a successful product
Q98: If a layout problem is solved by
Q101: _ are fees manufacturers pay to get
Q119: The project remains in one place and
Q122: Four hundred and eighty minutes of production
Q178: In what specific areas does the layout
Q317: A(n) _ line is a machine-paced product-oriented
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents