Consider the activities,durations,and predecessor relationships in the following network.Draw the network and answer the questions that follow.
a.What is the expected time for activity B?
b.What is the variance for activity B?
c.Based on the calculation of estimated times,what is the critical path?
d.What is the estimated time of the critical path?
e.What is the activity variance along the critical path?
f.What is the probability of completion of the project before week 42?
Correct Answer:
Verified
b.
c.A-C...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q16: What characteristics should be considered when selecting
Q43: Why do managers want to know the
Q86: Describe how time-cost tradeoffs for project activities
Q131: What options do project managers have to
Q133: The project manager and team can step
Q142: Why is identifying which path is the
Q143: Consider a project that consists of three
Q145: Phoebe B.Beebee is constructing a canal for
Q148: The following table contains a list of
Q149: The following table contains a list of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents