Table 2.11 -Using Table 2.11,if Activity B Is Crashed by 2 Weeks,what

Question 81

Multiple Choice

Table 2.11
Table 2.11    -Using Table 2.11,if activity B is crashed by 2 weeks,what is the new earliest completion time of the project? A) fewer than 11 weeks B) 11 weeks C) 12 weeks D) more than 12 weeks
-Using Table 2.11,if activity B is crashed by 2 weeks,what is the new earliest completion time of the project?


A) fewer than 11 weeks
B) 11 weeks
C) 12 weeks
D) more than 12 weeks

Correct Answer: