Multiple Choice
Table 2.10
-Using Table 2.10,what is the earliest possible completion time for activity E after crashing?
A) day 11
B) day 13
C) day 15
D) day 17
Correct Answer:
Verified
Related Questions
Table 2.10
-Using Table 2.10,what is the earliest possible completion time for activity E after crashing?
A) day 11
B) day 13
C) day 15
D) day 17
Correct Answer:
Verified