Use the process flow diagram to determine which of these events has the greatest net benefit.
A) reducing the flow time at Station A from 8 to 7 minutes
B) increasing the capacity at Station B to 8 units per hour
C) increasing the capacity at Station C to 7 units per hour
D) reducing the flow time at Station D from 9 to 8 minutes
Correct Answer:
Verified
Q5: The fifth step in Theory of Constraints
Q10: Consider consecutive processes A-B-C, where process A
Q17: The fourth step in Theory of Constraints
Q34: Table 7.1 Q35: The third step in Theory of Constraints Q39: According to the Theory of Constraints,the four Q40: Use the process flow diagram to determine