The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6. a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q76: The network below represents a project being
Q76: In PERT analysis, the identification of the
Q79: Given the project within the table below,calculate
Q80: The PERT pessimistic time estimate is an
Q90: In a PERT network, non-critical activities that
Q91: An activity on a PERT network has
Q92: A project being analyzed by PERT has
Q96: Which of the following statements regarding PERT
Q101: A project whose critical path has an
Q108: A project whose critical path has an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents