Your company keeps 15 days of materials inventory on hand to avoid shutdowns due to materials shortages. Carrying costs average $5,000 per day. A competitor keeps 12 days of inventory on hand, and the competitor's carrying costs average $3,000 per day. The non-value-added costs would be
A) $-0-.
B) $75,000.
C) $30,000.
D) $80,000.
Correct Answer:
Verified
Q42: Each unit of product requires 16 pounds
Q52: The purpose of trend reporting on nonvalue-added
Q81: Setup time for a product is 12
Q83: The continuous improvement subcycle of Kaizen costing
Q84: The maintenance subcycle is defined by what
Q85: Controlling the cost reduction process using Kaizen
Q86: A company has 5 days of finished
Q90: A company has 5 days of finished
Q92: A technique for improving performance of activities
Q96: Cheshire Cat Company sells one of its
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents