Solved

Villanova, Inc

Question 172

Multiple Choice

Villanova, Inc., has done a cost analysis for its production of rubber stamps. The following activities and cost drivers have been developed: Activity Cost Formula
Design $5,000 + $0.05 per machine hour
Machining $25,000 + $0.01 per machine hour
Setups $35 per batch
Purchasing $50 + $15 per purchase order
Following are the actual costs of producing 35,000 rubber stamps: 1,000 machine hours; 5 batches; 30 purchase orders
Design $5,080
Machining ?
Setups ?
Purchasing $600
The following variances were given in the activity performance report:
Design ?
Machining $40 F
Setups $15 F
Purchasing ?
What is the activity variance for design?


A) $40 F
B) $30 U
C) $15 F
D) $100 U

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents