Question 50

Essay

The critical path for this network is A - E - F and the project completion time is 22 weeks.
 The critical path for this network is A - E - F and the project completion time is 22 weeks.    ​   \begin{array} { c c c r r }  \text { Activity } & \begin{array} { c }  \text { Normal } \\ \text { Time } \end{array} & \begin{array} { c }  \text { Crash } \\ \text { Time } \end{array} & \begin{array} { c }  \text { Normal } \\ \text { Cost } \end{array} & \multicolumn{1}{c} { \begin{array} { c }  \text { Crash } \\ \text { Cost } \end{array} } \\ \hline \text { A } & 12 & 8 & 8,000 & 12,000 \\ \text { B } & 14 & 10 & 5,000 & 7,500 \\ \text { C } & 8 & 8 & 10,000 & 10,000 \\ \text { D } & 5 & 3 & 6,000 & 8,000 \\ \text { E } & 4 & 3 & 5,000 & 7,000 \\ \text { F } & 6 & 5 & 9,000 & 12,000 \\ \text { G } & 10 & 8 & 5,000 & 8,000 \end{array}  If a deadline of 17 weeks is imposed,give the linear programming model for the crashing decision.
 Activity  Normal  Time  Crash  Time  Normal  Cost \multicolumn1c Crash  Cost  A 1288,00012,000 B 14105,0007,500 C 8810,00010,000 D 536,0008,000 E 435,0007,000 F 659,00012,000 G 1085,0008,000\begin{array} { c c c r r } \text { Activity } & \begin{array} { c } \text { Normal } \\\text { Time }\end{array} & \begin{array} { c } \text { Crash } \\\text { Time }\end{array} & \begin{array} { c } \text { Normal } \\\text { Cost }\end{array} & \multicolumn{1}{c} { \begin{array} { c } \text { Crash } \\\text { Cost }\end{array} } \\\hline \text { A } & 12 & 8 & 8,000 & 12,000 \\\text { B } & 14 & 10 & 5,000 & 7,500 \\\text { C } & 8 & 8 & 10,000 & 10,000 \\\text { D } & 5 & 3 & 6,000 & 8,000 \\\text { E } & 4 & 3 & 5,000 & 7,000 \\\text { F } & 6 & 5 & 9,000 & 12,000 \\\text { G } & 10 & 8 & 5,000 & 8,000\end{array} If a deadline of 17 weeks is imposed,give the linear programming model for the crashing decision.

Correct Answer:

verifed

Verified

Let Ei = the earliest finish time for act...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents