Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q40: Describe the differences between a Gantt chart
Q66: What are the earliest activity start time
Q104: The network below represents a project being
Q104: Briefly describe the concept of cost/time trade-off
Q105: Draw the AOA and AON networks for
Q106: A network consists of the following list.Times
Q107: The network below represents a project being
Q107: How is the expected completion time of
Q113: A partially solved PERT problem is detailed
Q114: Describe in words how to calculate a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents