Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for each of the three activities?
b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q40: Describe the differences between a Gantt chart
Q107: How is the expected completion time of
Q111: PERT calculations typically include the duration variance
Q113: A partially solved PERT problem is detailed
Q114: Describe in words how to calculate a
Q115: Consider the network described in the table
Q115: Briefly discuss what is meant by critical
Q117: Pirmin's Bike Shop is behind on a
Q118: A network consists of the following list.Times
Q121: Consider the network presented in the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents