A firm is planning to set up an assembly line to assemble 40 units per hour,and 57 minutes per hour are productive.The time to perform each task and the tasks which precede each task are:
a.Draw a network diagram of precedence relationships.
b.Compute the required cycle time per unit in minutes.
c.Compute the theoretical minimum number of workstations required to produce 40 units per hour.
d.Balance this line using longest processing time.
e.What is the efficiency of the line obtained in part d?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q143: An assembly line with 11 tasks is
Q145: A work cell is required to make
Q146: An electronics manufacturer makes remote control devices
Q146: Brandon's computer shop has hired a consultant
Q149: A facility is trying to set up
Q150: An airport is trying to balance where
Q152: A manufacturing work cell has a takt
Q152: A firm operates a flow shop building
Q153: The flow and distance data in the
Q156: A work cell is scheduled to build
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents