The operations manager of a body and paint shop has five cars to schedule for repair.He would like to minimize the throughput time (makespan)to complete all work on these cars.Each car requires body work prior to painting.The estimates of the times required to do the body and paint work on each are as follows:
a.Chart the progress of these five jobs through the two centres on the basis of the arbitrary order
A→B→C→D→E.
b.After how many hours will all jobs be completed?
c.Use Johnson's rule to sequence these five jobs for minimum total duration.Show your work in
determining the job sequence.
d.The optimal sequence is ________.
e.Chart the progress of the five jobs in this optimal sequence.
f.After how many hours will all jobs be completed?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q126: There are 5 jobs (A, B, C,
Q127: Given the following chart of jobs assigned
Q128: A manufacturer has the following jobs waiting
Q129: Use Johnson's rule to determine the optimal
Q130: Find the sequence for the priority rules
Q131: At Morgan's Transformer Rebuilding,five jobs are ready
Q133: Use Johnson's rule to determine the optimal
Q134: The president of a consulting firm wants
Q135: Lockport Marine Services,Inc.wishes to assign a set
Q137: The emergency room at a hospital estimates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents