The _______________ probability distribution is typically used to describe uncertain activity times in a project.
A) beta
B) normal
C) binomial
D) exponential
Correct Answer:
Verified
Q63: A project consists of the following four
Q64: A project consists of the following four
Q65: A project consists of the following activities:
Q66: A project consists of the following four
Q67: A project consists of the following four
Q69: A project consists of the following four
Q70: The following table of probabilistic time estimates
Q71: The estimated variance for an activity with
Q72: The slack time for an activity can
Q73: The estimated variance for an activity with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents